ADU Rules and Permits in Montgomery County

Montgomery County generally allows accessory dwelling units on many single-family lots, as long as the unit meets zoning standards and passes building review. Most projects need ADU building permits for both zoning and construction, plus inspections before anyone moves in. Approval depends on your lot, your plans and the rules in force when you apply. Review queues can stretch, and spring construction slots fill early, so start planning months before your target build date. Here are nine things to understand before you draw up plans.
This article is general information. It is not legal advice. ADU rules change, and some towns inside the county set their own zoning. Confirm current requirements with Montgomery County’s Department of Permitting Services or your local jurisdiction before you design.
1. What Counts as an ADU
An accessory dwelling unit is a second, smaller home on the same lot as a single-family house. It has its own living space, kitchen and bathroom. The county’s accessory dwelling unit rules generally recognize two broad types:
- Attached units: built inside or onto the main house, such as a basement apartment or an addition
- Detached units: built as a separate structure, such as a backyard cottage or a converted detached garage
The type you choose shapes nearly every rule that follows, from setbacks to entrances.
2. Where ADUs Are Generally Allowed
ADUs are typically permitted in the county’s single-family residential zones. Your zone, lot size and existing buildings all affect what you can add. ADU zoning rules may also cover unit size, height, the number of ADUs per lot and owner occupancy.
Two more layers can apply:
- Municipal rules: Some cities and towns inside Montgomery County run their own zoning and permitting.
- HOA covenants: A homeowners association can restrict ADUs even where the county allows them.
Check the county, your municipality and your HOA before you pay for drawings.
3. Detached Units vs. Converted Space
Converted units reuse space you already have, such as a basement or attic. They rarely raise new setback questions. They still need proper egress windows, ceiling height, fire separation and safe utilities.
Detached units add a new structure to your yard. That brings property line setbacks, lot coverage limits and height caps into play. A detached unit also needs its own utility connections, which can add review steps.
The trade-off is simple. Conversions often move through review faster. Detached units offer more privacy for both households.
4. Separate Entrances
Every ADU needs its own way in and out. For attached units, the rules may limit where that door can go. The side or rear of the house is a common answer, which keeps the street view looking like a single-family home.
Settle the entrance location early. Moving a door late in design can mean new stairs, a new landing or a revised exterior wall. Detached units usually have more freedom, though the path to the door still needs safe access.
5. Parking
ADU parking rules have loosened in recent years, especially for homes near transit. Some lots may still need an added space. Others can rely on an existing driveway or street parking.
Your site plan should show where cars park today and where they’ll park after the ADU is finished. Reviewers check this during zoning compliance review, so a vague parking plan can send drawings back for revision.
6. What Your Plan Set Needs to Show
A complete submission saves weeks of back-and-forth. Plans for an ADU permit usually include:
- A site plan with the house, the ADU, lot lines, setbacks and parking
- Floor plans with room labels and dimensions
- Exterior elevations showing windows, doors and the entrance
- Structural details for new foundations, framing or openings in bearing walls
- Electrical, plumbing and mechanical layouts
- Egress and fire separation details
Every drawing must meet local building codes. The county adopts model codes and adds its own amendments, so a plan that passed in another jurisdiction may still need changes here.
7. Review Stages and Timing
Most ADU projects follow a similar sequence:
- Research: Confirm your zone, lot standards and any municipal or HOA limits.
- Application: Submit plans and forms to the permitting office.
- Zoning review: Reviewers check use, size, setbacks, entrance and parking.
- Building plan review: Reviewers check structure, fire safety, egress and systems.
- Other agency reviews: These may cover water and sewer, stormwater, trees or historic districts.
- Permit issuance: Construction can begin once the permit is issued.
- Inspections: Framing, electrical, plumbing, mechanical and final inspections follow the work.
- Rental licensing: A license or registration may be required before a tenant moves in.
Timing varies widely. A basement conversion with complete plans can clear review faster than a new detached unit with utility questions. Each round of reviewer comments adds time. Build a buffer into your schedule instead of counting on one clean pass.
8. Common Causes of Delays
- Incomplete plans or missing site details
- Setback or lot coverage conflicts found during review
- An entrance placed where the rules don’t allow it
- Basement ceilings or windows that fall short of height and egress standards
- Utility capacity or connection questions for detached units
- Slow responses to reviewer comments
- HOA or municipal limits discovered late
- Work started before approval, which can trigger a stop-work order
Most of these trace back to planning. Catch them on paper, where fixes cost the least.
9. Staying Compliant After Approval
An issued permit isn’t the finish line. Inspections confirm the work matches the approved plans. Changes made in the field may need a permit revision.
Many ADU regulations in Montgomery County also apply after construction ends. They can cover rental licensing, occupancy and how the unit is used. Keep your approved plans, inspection records and final sign-off in one folder. A future buyer or lender may ask for them.
Turning ADU Plans Into Approved Construction
Every stage of ADU building permits rewards careful planning, from the first site plan to the final inspection. Chase Remodeling manages the permit process for projects that require one, including additions and structural changes. We know Montgomery County’s requirements, and we don’t start construction until permits are approved. One dedicated project manager coordinates the trades and tracks your schedule. If your ADU involves finishing a basement or building an addition, our team can help shape the scope before plans go in.
Here’s what happens next. Contact Chase Remodeling with a few details about your lot and goals. We’ll follow up to learn more and schedule a free in-home consultation. From there, we’ll walk through scope, timing and the permit path for your project.
Frequently Asked Questions
Do I need ADU building permits for a basement apartment?
Yes, in most cases. Turning a basement into a separate living unit usually needs zoning approval, building permits and inspections.
Can I build a detached ADU on any lot?
No. Your zone, lot size, setbacks and coverage limits decide what fits. Some lots can only support an attached or converted unit.
Does an ADU need its own parking space?
It depends on your lot and location. Parking rules have eased near transit, but some properties still need to show added space.
How long does ADU approval take?
It varies by project type, plan quality and reviewer comments. Complete plans and quick responses keep things moving.
Can I start building while my permit is under review?
No. Starting early can lead to stop-work orders, fines or tear-outs. Wait until the permit is issued.